Impact Intelligence for change orders
The Impact Intelligence Verification Graph Engine (VGE) maps change order dependencies across:
- Submittals, RFIs, and ASI revision chains
- Procurement lead times and installation sequencing
- Subcontractor scopes and trade coordination
- Critical path activities and schedule successors
Preview mode lets you model change order impact before field execution - with cost and schedule delta estimates across trades.
Submittal cascade analysis
See the full cascade before approving a change order:
- Submittal updates and RFI generation
- Subcontractor scope changes triggered
- ASI revisions and specification impacts
Schedule impact mapping
Understand critical path changes before committing to field work:
- Procurement and lead time effects
- Installation sequencing and successor activities
- Float consumption and milestone shifts
Multi-trade coordination
Identify conflicts across trades before mobilization:
- Cross-trade scope collisions (HVAC, electrical, plumbing)
- Spatial and sequencing conflicts
- Shared resource and access constraints
Console preview
Change intelligence report
Seed change
Scope change: HVAC spec revision - chiller capacity 200T → 250T
Change impact
34 of 180 nodes (19%)
across 4 domains
Severity hotspots
4
critical
NRE estimate
$45K – $82K
likely $62K
Schedule delta
+14d
critical path
Impact cascade / sample path
Spec change invalidates approved shop drawings - resubmittal required
via submittals
3 RFIs reopened for structural coordination
via rfi
2 subcontractor schedules delayed
via scheduling
4 procurement line items need requoting
via procurement
Budget contingency draw: $18K
via cost_control
1 another scope change overlaps this submittal package
- └─ CO-0147 Electrical panel relocation - Level 3 west wing 2 shared nodes pending approval
Verification pack / draft
- 3 submittal resubmissions
- 3 RFI resolutions
- 4 procurement requotes
- 2 schedule impact assessments
Cost estimate: NRE $45K – $82K (likely $62K)
- ├─ Resubmittal engineering: $12K – $18K (shop drawing revisions)
- ├─ Subcontractor re-pricing: $8K – $14K (4 line items affected)
- ├─ Schedule penalty: +14d delays MEP rough-in by 2 weeks
- ├─ Contingency draw: $18K from project contingency reserve
The problem
Scope changes cascade silently across trades
An HVAC design revision seems minor until you discover it affects 12 submittals, 4 RFIs, and 3 subcontractor scopes. When another change order introduces a collision, the compounding impact is only visible after field mobilization. By then, you're managing rework, schedule delays, and cost overruns.
Hidden cost of blind changes
- A mechanical design change triggers 8 downstream submittals and 2 ASIs with revised sketches, discovered only after subcontractor mobilization
- Material substitution approved without checking procurement lead times, causing a 4-week critical path delay and forcing schedule recovery
- Electrical scope change collides with plumbing rough-in, requiring demobilization and rework across 3 floors
- Permit condition change triggers 6 inspection hold points and re-inspections, delaying earned progress and affecting the current pay application draw approval
Key capabilities
Active intelligence for construction changes.
Submittal cascade analysis
Trace design revisions through submittal dependencies, shop drawings, product data sheets, and approval workflows. Identify all affected submittals, their current status, and re-approval requirements before issuing the change order.
RFI impact mapping
Map change orders to open RFIs, pending clarifications, and decision dependencies. Understand which RFIs are resolved, which require ASIs or supplemental sketches, and which introduce new clarification requirements.
Subcontractor scope propagation
Track scope changes across subcontractor agreements, work packages, and trade coordination. Identify affected subs, contract modification requirements, and multi-trade sequencing impacts before mobilization.
Schedule dependency checks
Analyze critical path impacts, successor activity delays, and milestone compression requirements. Preview schedule adjustments, float consumption, and liquidated damages exposure before approving scope changes.
Material procurement impact
Connect material substitutions to procurement lead times, supplier capacity, and installation sequencing. Identify long-lead items, supply chain risks, and inventory coordination requirements.
Cost-to-complete recalculation
Propagate scope changes through budget forecasts, contingency reserves, and cost-to-complete projections. Track change order accumulation, owner allowances, and GMP compliance in real time.
AIA billing alignment
Ensure change orders flow through AIA G702/G703 (or equivalent) payment applications, your schedule of values, and payment requisitions. Prevent billing mismatches, owner disputes, and draw rejections.
Permit and inspection triggers
Identify scope changes requiring permit amendments, additional inspections, or authority approvals. Preview permitting workflows, inspection hold requirements, and certificate of occupancy impacts.
How it works
From change signal to verified action.
Graph model for construction dependencies
EquatorOps builds a dependency graph of your project: change orders, submittals, RFIs, subcontractor scopes, schedule activities, procurement items, and AIA billing line items. Each entity and relationship is tracked in a unified graph structure.
Define impact rules for AEC workflows
Configure rules that match your project execution model: design revisions trigger submittal re-approvals, material substitutions check procurement lead times, scope changes validate subcontractor agreements, schedule accelerations analyze critical path float.
Preview cascades before approval
Before approving a change order, see the complete cascade: affected submittals, impacted RFIs, subcontractor modifications, critical path delays, procurement lead time risks, and billing adjustments. Understand the full project impact in seconds.
Detect multi-trade conflicts
When multiple change orders affect overlapping scopes, EquatorOps identifies collisions: mechanical changes conflicting with electrical rough-in, structural modifications affecting architectural finishes, plumbing revisions impacting fire protection.
Propagate approved changes
Once approved, Impact Intelligence surfaces the downstream updates: submittal statuses flagged for re-approval, RFI responses and ASIs queued, subcontractor notifications drafted, schedule adjustment recommendations generated, procurement lead time alerts raised, and AIA billing line item adjustments suggested.
Verification packs for field coordination
Generate verification packs for each change order: submittal re-approval checklist, RFI resolution confirmations, subcontractor scope acknowledgments, inspection hold requirements, material delivery confirmations.
Real-time coordination dashboard
Monitor project health across all trades: submittal approval velocity, RFI aging, subcontractor scope alignment, schedule critical path status, procurement on-time delivery, AIA billing reconciliation.
Hybrid graph model
The construction graph model captures the full lifecycle of scope changes: design revisions flow through submittals and shop drawings, material substitutions propagate through procurement and installation, schedule changes cascade through successor activities and trade sequencing. Each change order, submittal, RFI, subcontractor agreement, schedule activity, and billing line item becomes a node; dependencies become edges.
Submittal dependencies
Design revisions trigger submittal re-approvals, shop drawing updates, and product data revisions. Edges capture approval workflows, resubmittal requirements, and design coordination dependencies.
Trade coordination
Subcontractor scopes interconnect through rough-in sequencing, finish coordination, and MEP clash resolution. Edges track work package dependencies, mobilization sequencing, and multi-trade conflicts.
Schedule propagation
Schedule activities link through finish-to-start, start-to-start, and finish-to-finish relationships. Edges capture critical path logic, float consumption, and milestone compression impacts.
Construction impact scenarios
Real change scenarios in construction.
Impact Intelligence adapts to your domain’s change patterns, compliance frameworks, and verification workflows. These are representative output examples from the VGE computation pipeline.
Construction
Submittal approval velocity, RFI resolution time, subcontractor acknowledgment rate, schedule float consumption, procurement on-time deliveryTrigger
Design revision scope change
Impact
12 submittals require re-approval, 4 RFIs need ASIs or supplemental sketches, 3 subcontractor scopes modified, 8 schedule activities shifted, 2 procurement orders adjusted
Verification Pack
Submittal re-approval checklist, RFI response and ASI log, subcontractor scope change notices, updated CPM schedule, procurement lead time confirmations
Metrics
Submittal approval velocity, RFI resolution time, subcontractor acknowledgment rate, schedule float consumption, procurement on-time delivery
Construction
Procurement lead time variance, schedule critical path impact, subcontractor standby costs, billing reconciliation accuracy, inspection approval timeTrigger
Material substitution
Impact
6-week procurement delay, 4 installation activities rescheduled, 2 subcontractor crews demobilized, 3 AIA billing line items adjusted, 1 inspection hold triggered
Verification Pack
Procurement lead time analysis, schedule compression plan, subcontractor demobilization notices, AIA G703 adjustments, inspection coordination log
Metrics
Procurement lead time variance, schedule critical path impact, subcontractor standby costs, billing reconciliation accuracy, inspection approval time
Construction
Critical path float remaining, trade overlap conflicts, overtime cost tracking, inspection approval rate, contingency reserve balanceTrigger
Schedule acceleration
Impact
Critical path compressed 3 weeks, 8 activities overlap trades, 4 subcontractors require overtime, 2 permit inspections expedited, GMP contingency reduced $45K
Verification Pack
Compressed schedule narrative, trade overlap coordination plan, subcontractor overtime approvals, expedited inspection requests, contingency draw justification
Metrics
Critical path float remaining, trade overlap conflicts, overtime cost tracking, inspection approval rate, contingency reserve balance
Construction
Subcontractor scope alignment, trade delay days, submittal approval backlog, billing accuracy, milestone on-time completionTrigger
Subcontractor change order
Impact
3 work packages modified, 2 successor trades delayed, 5 submittals pending re-approval, 4 AIA billing line items recalculated, 1 milestone at risk
Verification Pack
Subcontractor scope modification agreements, trade coordination schedule, submittal re-approval tracker, AIA G702 revision, milestone recovery plan
Metrics
Subcontractor scope alignment, trade delay days, submittal approval backlog, billing accuracy, milestone on-time completion
Construction
Inspection approval time, subcontractor compliance rate, submittal rejection rate, schedule recovery velocity, CO issuance probabilityTrigger
Permit condition change
Impact
6 inspection holds required, 3 subcontractor scopes affected, 2 submittals rejected pending compliance, 4 schedule activities delayed, 1 certificate of occupancy at risk
Verification Pack
Inspection hold coordination plan, subcontractor compliance notifications, submittal compliance re-review, schedule recovery analysis, CO readiness assessment
Metrics
Inspection approval time, subcontractor compliance rate, submittal rejection rate, schedule recovery velocity, CO issuance probability
Impact Intelligence for Construction
Operational scale that makes impact analysis possible.
VGE runs on tenant-owned data: schema depth, API breadth, and deterministic telemetry that keeps change reviews consistent.
Domain providers
15+
5 cross-industry baseline + 10 domain-specific providers (composition structures, compliance, verification, 3D/geometric, procurement, inventory, capital assets, execution chains), each self-describing with SemVer and cost tiers.
Sync analysis
≤2s
Typical graph traversal (≤1K nodes) with batch-first providers and per-request caching.
Async analysis
≤30s
Complex traversals (≤10K nodes) with optional Redis acceleration and per-provider timing.
Impact demo
Impact Intelligence for Construction
Preview change impact, severity scoring, and verification packs before approvals.
Change impact
34 nodes
Projected change
Severity hotspots
4
Projected change
NRE estimate
$62K
Projected change
Schedule delta
+14d
Projected change
Sample finding
See the full cascade before approving a change order:
Impact cascade
Graph model for construction dependencies
Submittal dependencies
Trade coordination
Schedule propagation
API preview
Schema-stable endpoints for impact intelligence.
Impact Intelligence is designed as a tenant-owned API surface with preview-first semantics, deterministic run snapshots, and export-ready results.
Preview vs apply
Every request can run in preview mode to generate impact results without mutating data. Apply mode uses idempotency keys to persist verification packs safely.
View developer docsPOST Start impact analysis
Seed an impact analysis for a change order, design revision, or material substitution. Traverses submittals, RFIs, subcontractor scopes, and schedule activities.
POST /api/v1/change-controls/{id}/impact/run The ChangeControl record (created separately) carries the change details: structural steel specification revision from ASTM A992 to ASTM A913 Gr. 65 for wide-flange members at levels 3–7, spec section 05 12 00, PCO-0047.
Request
{
"detect_collisions": true
} Response
{
"schema_version": "vge.graph_result.v1",
"run_id": 198,
"nodes": [
{
"node_ref": {
"resource_type": "submittal",
"resource_id": 504712,
"display_name": "Submittal 05 12 00-003 - Structural Steel Shop Drawings (Levels 3–7)",
"display_code": "SUB-05-12-00-003",
"status": "Approved - Resubmittal Required",
"tags": [
"Spec 05 12 00",
"Shop Drawings",
"Turner Steel LLC"
]
},
"severity": 0.94,
"depth": 1
},
{
"node_ref": {
"resource_type": "rfi",
"resource_id": 504801,
"display_name": "RFI-247 - Connection detail adequacy for A913 Gr. 65 moment frames",
"display_code": "RFI-247",
"status": "Open - Pending Structural EOR Response",
"tags": [
"Structural",
"Moment Connections",
"Spec 05 12 00"
]
},
"severity": 0.91,
"depth": 1
},
{
"node_ref": {
"resource_type": "subcontractor_scope",
"resource_id": 504901,
"display_name": "Turner Steel LLC - Structural Steel Erection (Pkg 05A)",
"display_code": "SUB-PKG-05A",
"status": "Scope Modification Required",
"tags": [
"Steel Erection",
"Levels 3–7",
"CO Pending"
]
},
"severity": 0.89,
"depth": 2
},
{
"node_ref": {
"resource_type": "schedule_activity",
"resource_id": 505001,
"display_name": "Activity 3140 - Steel Erection Levels 5–7",
"display_code": "ACT-3140",
"status": "Not Started - Predecessor Delayed",
"tags": [
"Critical Path",
"Steel Erection",
"Milestone: Topping Out"
]
},
"severity": 0.86,
"depth": 2
},
{
"node_ref": {
"resource_type": "submittal",
"resource_id": 504715,
"display_name": "Submittal 05 05 23-001 - Welding Procedure Specifications (WPS)",
"display_code": "SUB-05-05-23-001",
"status": "Approved - Resubmittal Required",
"tags": [
"Spec 05 05 23",
"Welding",
"AWS D1.1"
]
},
"severity": 0.85,
"depth": 2
},
{
"node_ref": {
"resource_type": "inspection_hold",
"resource_id": 505101,
"display_name": "Special Inspection - Structural Welding (Levels 3–7)",
"display_code": "INSP-STL-037",
"status": "Hold - Revised WPS Required",
"tags": [
"IBC Special Inspection",
"Welding",
"Third-Party"
]
},
"severity": 0.82,
"depth": 3
}
],
"edges": [
{
"source": {
"resource_type": "change_order",
"display_code": "PCO-0047"
},
"target": {
"resource_type": "submittal",
"display_code": "SUB-05-12-00-003"
},
"edge_type": "TRIGGERS_RESUBMITTAL",
"provider": "submittals",
"label": "Spec change invalidates approved shop drawings - resubmittal required"
},
{
"source": {
"resource_type": "change_order",
"display_code": "PCO-0047"
},
"target": {
"resource_type": "rfi",
"display_code": "RFI-247"
},
"edge_type": "GENERATES_RFI",
"provider": "design_coordination",
"label": "A913 Gr. 65 moment frame connections require EOR confirmation"
},
{
"source": {
"resource_type": "submittal",
"display_code": "SUB-05-12-00-003"
},
"target": {
"resource_type": "subcontractor_scope",
"display_code": "SUB-PKG-05A"
},
"edge_type": "MODIFIES_SCOPE",
"provider": "trade_coordination",
"label": "Revised shop drawings change erection sequence for Turner Steel"
},
{
"source": {
"resource_type": "subcontractor_scope",
"display_code": "SUB-PKG-05A"
},
"target": {
"resource_type": "schedule_activity",
"display_code": "ACT-3140"
},
"edge_type": "DELAYS_ACTIVITY",
"provider": "scheduling",
"label": "Scope modification delays steel erection start by 14 days"
},
{
"source": {
"resource_type": "change_order",
"display_code": "PCO-0047"
},
"target": {
"resource_type": "submittal",
"display_code": "SUB-05-05-23-001"
},
"edge_type": "TRIGGERS_RESUBMITTAL",
"provider": "submittals",
"label": "A913 Gr. 65 requires updated welding procedure specifications per AWS D1.1"
},
{
"source": {
"resource_type": "submittal",
"display_code": "SUB-05-05-23-001"
},
"target": {
"resource_type": "inspection_hold",
"display_code": "INSP-STL-037"
},
"edge_type": "HOLDS_INSPECTION",
"provider": "quality_gate",
"label": "Special inspection on hold until revised WPS approved"
}
],
"stats": {
"node_count": 34,
"edge_count": 58,
"provider_counts": {
"submittals": 12,
"design_coordination": 4,
"trade_coordination": 8,
"scheduling": 6,
"quality_gate": 4
},
"truncated": false,
"collisions": {
"collision_count": 0,
"collision_severity": "NONE"
}
}
} GET Retrieve impact snapshot
Get the full change impact with severity scores across submittals, RFIs, subcontractor scopes, and schedule activities.
GET /api/v1/change-controls/{id}/impact Response
{
"run_id": 198,
"change_control_id": 47,
"summary": {
"node_count": 34,
"severity_hotspots": 4,
"top_severity_nodes": [
{
"node_key": "submittal:504712:head",
"display": "SUB-05-12-00-003 - Structural Steel Shop Drawings",
"severity": 0.94
},
{
"node_key": "rfi:504801:head",
"display": "RFI-247 - Moment frame connection adequacy",
"severity": 0.91
},
{
"node_key": "subcontractor_scope:504901:head",
"display": "Turner Steel LLC - Pkg 05A scope modification",
"severity": 0.89
},
{
"node_key": "schedule_activity:505001:head",
"display": "ACT-3140 - Steel Erection Levels 5–7 (critical path)",
"severity": 0.86
}
],
"schedule_impact_days": 14,
"nre_estimate_likely": 62050
}
} GET Explain proof path
Trace why a specific submittal, subcontractor scope, or schedule activity is impacted, auditable at every dependency hop.
GET /api/v1/change-controls/{id}/impact/explain?node_key=schedule_activity:505001:head Response
{
"run_id": 198,
"target_node_key": "schedule_activity:505001:head",
"path_node_keys": [
"change_order:47:head",
"submittal:504712:head",
"subcontractor_scope:504901:head",
"schedule_activity:505001:head"
],
"path_edges": [
{
"edge_type": "TRIGGERS_RESUBMITTAL",
"provider": "submittals",
"label": "PCO-0047 invalidates approved shop drawings SUB-05-12-00-003"
},
{
"edge_type": "MODIFIES_SCOPE",
"provider": "trade_coordination",
"label": "Revised shop drawings require Turner Steel erection sequence change"
},
{
"edge_type": "DELAYS_ACTIVITY",
"provider": "scheduling",
"label": "Scope modification pushes steel erection start by 14 days - critical path impacted"
}
],
"notes": "3-hop path: change order → shop drawing resubmittal → subcontractor scope modification → schedule activity delay. ACT-3140 is on the critical path to topping out milestone; 14-day delay consumes all remaining float."
} GET Detect cross-change collisions
Find where concurrent change orders create multi-trade conflicts across shared scope areas.
GET /api/v1/change-controls/{id}/impact/collisions Response
{
"collision_count": 2,
"colliding_change_ids": [
44,
51
],
"collision_severity": "HIGH",
"top_overlapping_nodes": [
{
"node_key": "subcontractor_scope:504901:head",
"severity": 0.89,
"change_ids": [
47,
44
],
"display": "Turner Steel LLC - Pkg 05A overlaps with PCO-0044 (fireproofing specification change affecting levels 3–5)"
},
{
"node_key": "schedule_activity:505001:head",
"severity": 0.86,
"change_ids": [
47,
51
],
"display": "ACT-3140 Steel Erection Levels 5–7 - overlaps with PCO-0051 (curtain wall anchor embed revision)"
}
]
} POST Generate verification pack
Generate submittal re-approval checklists, RFI resolution confirmations, and subcontractor scope acknowledgments in preview or apply mode.
POST /api/v1/change-controls/{id}/verification-pack/generate Request
{
"mode": "preview"
} Response
{
"proposed_validations": [
{
"validation_type": "document_review",
"validation_meta": {
"description": "Resubmittal required for structural steel shop drawings - spec change ASTM A992 to ASTM A913 Gr. 65, levels 3–7",
"affected_nodes": [
"submittal:504712:head",
"submittal:504715:head",
"submittal:504718:head"
],
"spec_sections": [
"05 12 00 - Structural Steel Framing",
"05 05 23 - Welding"
]
}
},
{
"validation_type": "document_review",
"validation_meta": {
"description": "RFI-247 requires structural EOR confirmation - moment frame connection details for A913 Gr. 65 wide-flange members",
"affected_nodes": [
"rfi:504801:head",
"rfi:504803:head"
],
"response_deadline": "2026-02-15"
}
},
{
"validation_type": "checklist",
"validation_meta": {
"description": "Turner Steel LLC scope modification acknowledgment - revised erection sequence and welding procedures for levels 3–7",
"affected_nodes": [
"subcontractor_scope:504901:head"
],
"contract_reference": "Subcontract 05A-2025-Turner"
}
},
{
"validation_type": "inspection",
"validation_meta": {
"description": "Special inspection hold - structural welding inspections paused pending revised WPS approval per IBC 1705.2",
"affected_nodes": [
"inspection_hold:505101:head"
]
}
}
],
"proposed_external_acknowledgements": [
{
"target_type": "SUBCONTRACTOR",
"target_id": 3041,
"reason": "Turner Steel LLC must acknowledge scope modification and submit revised erection plan for ASTM A913 Gr. 65 members"
},
{
"target_type": "SUBCONTRACTOR",
"target_id": 3055,
"reason": "Metro Fireproofing Inc. must confirm spray-applied fireproofing adhesion specs remain valid for A913 Gr. 65 flanges"
}
]
} POST Compute cost estimate
Estimate NRE costs (scope changes, documentation updates, replanning) and recurring impact (subcontractor rate changes, material cost deltas) with min/likely/max uncertainty bounds and schedule impact.
POST /api/v1/change-controls/{id}/cost-estimate Response
{
"estimate_id": 1088,
"impact_analysis_run_id": 198,
"line_items": [
{
"cost_driver_type": "nre",
"description": "Turner Steel LLC - scope modification for A913 Gr. 65 erection sequence, revised connection details, and updated welding procedures (levels 3–7)",
"quantity": 1,
"unit_rate": 28500,
"cost_phase": "nre",
"min_cost": 24000,
"likely_cost": 28500,
"max_cost": 35000,
"confidence": 0.85
},
{
"cost_driver_type": "nre",
"description": "Structural EOR review - revised connection details, moment frame analysis, and delegated design resubmittal for A913 Gr. 65",
"quantity": 80,
"unit_rate": 195,
"cost_phase": "nre",
"min_cost": 12000,
"likely_cost": 15600,
"max_cost": 20000,
"confidence": 0.82
},
{
"cost_driver_type": "nre",
"description": "Submittal re-approvals - shop drawings, WPS revisions, and mill certificate updates across 12 affected submittals",
"quantity": 12,
"unit_rate": 650,
"cost_phase": "nre",
"min_cost": 6000,
"likely_cost": 7800,
"max_cost": 10500,
"confidence": 0.88
},
{
"cost_driver_type": "nre",
"description": "Third-party special inspection - revised structural welding inspections per updated WPS, levels 3–7",
"quantity": 1,
"unit_rate": 4200,
"cost_phase": "nre",
"min_cost": 3500,
"likely_cost": 4200,
"max_cost": 5800,
"confidence": 0.8
},
{
"cost_driver_type": "nre",
"description": "Overtime and re-sequencing costs - compressing successor activities to recover 14-day schedule impact on critical path",
"quantity": 1,
"unit_rate": 5950,
"cost_phase": "nre",
"min_cost": 4000,
"likely_cost": 5950,
"max_cost": 8500,
"confidence": 0.72
},
{
"cost_driver_type": "recurring",
"description": "Per-ton material cost increase - ASTM A913 Gr. 65 vs ASTM A992 wide-flange sections (82 tons affected)",
"quantity": 82,
"unit_rate": 45,
"cost_phase": "recurring",
"min_cost": 28,
"likely_cost": 45,
"max_cost": 62,
"confidence": 0.9,
"justification": "Mill quote for A913 Gr. 65 W14 shapes: +$45/ton vs current A992 pricing, 82 tons at levels 3–7"
}
],
"nre_range": {
"min": 49500,
"likely": 62050,
"max": 79800
},
"recurring_range": {
"min": 28,
"likely": 45,
"max": 62,
"currency": "USD",
"description": "Per-ton recurring cost increase from ASTM A913 Gr. 65 specification upgrade"
},
"schedule_impact": {
"min_schedule_days": 8,
"likely_schedule_days": 14,
"max_schedule_days": 21,
"critical_path_nodes": [
"schedule_activity:505001:head"
]
},
"confidence": 0.83,
"confidence_notes": "Estimate calibrated from your operational data. Subcontractor change order negotiation and steel mill lead time are the primary uncertainty drivers.",
"justification_summary": "Structural steel spec revision ASTM A992 → ASTM A913 Gr. 65 drives $62K NRE (Turner Steel scope modification, structural EOR re-review, 12 submittal re-approvals, special inspection revisions, schedule recovery costs) plus $45/ton recurring material cost increase across 82 tons. Critical path delay of 14 days driven by shop drawing resubmittal and revised erection sequencing."
} GET Export impact graph
Export the full impact graph as JSON, CSV, or GraphML for integration with project management, scheduling, or AIA billing systems.
GET /api/v1/impact-analysis-runs/{run_id}/export?format=graphml Preview endpoints reflect the planned VGE surface. Final routes may adjust as the engine deploys to production.
FAQ
Common questions about Impact Intelligence for construction.
How does Impact Intelligence handle multi-trade coordination?
EquatorOps tracks dependencies across mechanical, electrical, plumbing, fire protection, structural, and architectural scopes. When a change order affects one trade, the system identifies overlapping work packages, rough-in sequencing conflicts, and finish coordination requirements across all trades. You see multi-trade collisions before mobilization.
Can Impact Intelligence analyze schedule compression impacts?
Yes. When you accelerate the schedule, Impact Intelligence analyzes critical path compression, float consumption, trade overlap conflicts, subcontractor overtime requirements, and milestone recovery plans. You understand schedule compression risks before committing to aggressive timelines.
How does this integrate with AIA billing workflows?
Change orders flow through AIA G702/G703 (or equivalent) payment applications, schedule of values line items, and payment requisitions. When a scope change is approved, Impact Intelligence flags all affected SOV line items for adjustment, preventing payment application mismatches and owner disputes.
What about GC-subcontractor coordination?
Impact Intelligence tracks subcontractor agreements, work package scopes, and trade coordination requirements. When a change order affects a subcontractor scope, the system identifies contract modification requirements, mobilization impacts, and multi-trade sequencing adjustments. You coordinate with subs before issuing change notices.
How does Impact Intelligence handle field vs office coordination?
Verification packs bridge office approvals and field execution: submittal re-approval checklists for site teams, RFI resolution confirmations for trade foremen, inspection hold requirements for superintendents, material delivery schedules for logistics. Field teams receive actionable coordination documents, not just approval notices.
Can this preview permit and inspection impacts?
Absolutely. When a scope change requires permit amendments or additional inspections, Impact Intelligence identifies permitting workflows, inspection hold requirements, authority approval timelines, and certificate of occupancy impacts. You understand permitting risks before executing field work.
How does this prevent submittal cascade surprises?
Impact Intelligence maps design revisions to all affected submittals, shop drawings, product data sheets, and approval workflows. Before approving a change order, you see which submittals require re-approval, which are already in review, and which introduce new coordination requirements. No post-approval submittal surprises.
What about procurement lead time impacts?
Material substitutions automatically trigger procurement lead time analysis: supplier capacity checks, long-lead item identification, delivery schedule adjustments, and installation sequencing impacts. You understand supply chain risks before committing to material changes.